rate analysis of m concrete in india

Rate Analysis of Concrete - CivilJungle

This calculation calculates of cement, sand, concrete ( concrete = Cement + Sand + aggregate mixture this call concrete) for materials. Concrete is used a sum different proportions 1:0.5:1,

More

Rate Analysis of M30 Grade Concrete (Manual RMC)

in the above format, we have given the format of m30 concrete ready mix, but while preparing the actual rate analysis you should visit your site location and then visit the around raw material

More

Rate analysis for concrete - calculate quantity and cost

Ans. INR 6839 is cost and rate analysis for 1 cum concrete of M10 (1:3:6). step 11 : rate per sq m for concrete m10, consider thickness of concrete structure is 150mm thick so Area of concrete

More

Rate Analysis Of Concrete - M25 Concrete Example Rate

Volume of Cement = 1/4 x 1.55 Volume of Sand = 1/4 x 1.55 Volume of Coarse Aggregate = 2/4 x 1.55 From the IS Code standard, Assuming the water-cement ratio for M20 is 0.5 The reason

More

Rate analysis for M20 concrete - Civil Sir

Rate analysis for concrete is comprise of following:- 1) quantity and cost of material ( cement sand aggregate and water quantity and their cost) 2) water charges ( 1 tanker) 3) overhead

More

Rate analysis for Concrete- Step by Step calculation with

Step -1 Write all the known values of the materials Here we should know that, Total Concrete = 10 m3 M15 means the ratio of ingredient in concrete shoud be (Cement:Sand:Aggregate) =

More

How to do rate Analysis For Concrete? - Civil Lead

1. Quantity of material and Its cost 2. Labour cost 3. Cost of equipment or Tools and plants ( 1.5%) 4. Water charges (1.5%) 5. Overhead expenses (2 to 5%) 6. Contractor profit (10%)

More

Rate Analysis of RCC (Reinforcement Cement Concrete)

Rate Analysis for Concrete Excel So, the total volume of required materials is taken as 1.54 m3 for 1 m 3 of wet concrete. No. of Cement Bags: Volume of cement necessary for 1 m 3 of

More

Ready Mixed Concrete - Ready Mix Concrete Latest Price

Acc Rmc Ready Mix Concreate Grade M10, in Lucknow. ₹ 4,900/ Cubic Meter Get Latest Price. Grade Standard: M10. Location/City: Lucknow. We supply quality ACC Ready mix concreate

More

ANALYSIS OF RATES

i) rate as per item (a) 1971.20 Out turn of PRR Earth work compaction considered 708.00 cum per day ordinarily Hire and running charges of PRR as per mechanical wings comes to Rs 269.00

More

Rate analysis for M20 concrete - Civil Sir

2 天前  Rate analysis for concrete is comprise of following:- 1) quantity and cost of material ( cement sand aggregate and water quantity and their cost) 2) water charges ( 1 tanker) 3) overhead expenses (3%) 4) cost of equipment and tools (2%) 5) contractor profit (10%) 6) labour rate and cost. Rate analysis for 1 cum concrete of M20 (1:1.5:3)

More

Rate Analysis Of Concrete - M25 Concrete

2022-11-20  Volume of Cement = 1/4 x 1.55 Volume of Sand = 1/4 x 1.55 Volume of Coarse Aggregate = 2/4 x 1.55 From the IS Code standard, Assuming the water-cement ratio for M20 is 0.5 The reason for that 1.55 has been

More

How to do rate Analysis For Concrete? - Civil Lead

2022-11-18  1. Quantity of material and Its cost 2. Labour cost 3. Cost of equipment or Tools and plants ( 1.5%) 4. Water charges (1.5%) 5. Overhead expenses (2 to 5%) 6. Contractor profit (10%) Rate Analysis for 1 cum of M15 (1:2:4) Quantity of material and its cost Cement = 1.54/7 = 0.22 cum × 28.8 = 6.336 bags Sand = 0.22 × 2 = 0.44 cum

More

Quantity and Rate Analysis for Reinforced Concrete

a) Bags of cement required: Volume of cement required for 1m 3 of Concrete = =0.28 m 3 Then number of bags of cement (volume of one bag of cement = 0.0347 m 3 ) = = 8.07 bags of cement. b) Volume of Sand required: Volume of sand required = = 0.42 m 3 of sand. c) Volume of Coarse Aggregate Required

More

Rate analysis for PCC 1:4:8 (M7.5) - calculate

2 天前  Ans. INR 4845 is cost and rate analysis for 1 cum PCC 1:4:8 (M7.5). step 11 : rate per sq m for PCC 1:4:8 (m7.5), consider thickness of concrete structure is 150mm thick so Area of concrete structure in square metre = 1m3/0.15m =

More

Analysis of Rates of Building Construction in

2022-11-20  Earth work in Filling : Mazdoor = 18 (% cum) Mason = 0.5 Cement concrete : Mazdoor = 15 in foundation Mason =1.5 Bhishti = 2 Cement concrete : Mazdoor = 15 Mason = 1 Bhishti = 2.5 R. Cement concrete : Mazdoor = 40

More

Rate analysis of brickwork - calculate quantity and cost

2 天前  Rate analysis for 1m2 of brickwork masonry For calculation rate per sq m of brickwork, We have brickwork volume = 1m3 and width of brick with mortar = 0.1m, then area of brickwork = 1/0.1 = 10m2. 10m2 brickwork cost = INR 7384, so rate and cost per sq meter of brickwork = 7384/10= 738.4 = INR 740 Rate per square metre for brickwork is INR 740.

More

Best Rate Analysis Excel Sheets For Civil Engineering Works

Brick Bats Cement Concrete (1:4:8 Ratio) Rate Analysis Excel Sheet RCC slabs sometimes crack and let rainwater through. Therefore, it is important to develop a waterproof roof panel that can provide a leak-proof environment for the interior of the building. Download Link 3. Sand Filling In Foundation Rate Analysis SpreadSheet

More

What will be the cost of M25 grade concrete ?/How to

2021-9-24  The cost of M25 grade concrete per cu ft. = [INR 8371.69/- ÷ 35.314] ( 1CUM = 35.314 cu ft.) = INR 237.06/ - per cu ft. For contractor: If the concrete work is handed over to any contractor, then you have to add 10% extra as profit. The cost of M25 grade concrete done by a contractor = [INR 8371.69/- + 10% of INR 8371.69/-]

More

Rate Analysis Of Brickwork Rate Analysis Of

2021-6-26  Rate analysis of brickwork, rate analysis of brick masonry, rate analysis of cement mortar in brickwork, superstructure brickwork and brick superstructure. Home; About; Contact; ... Kg for cement, M 3 for sand, 1000

More

Rate Analysis for Concrete - Civil Scoops

2 天前  Introduction of Rate Analysis for Concrete Step 1: Estimation of Materials 1.1 Bags of cement required: 1.2 Volume of Sand required: 1.3 Volume of Coarse Aggregate Required 1.4 Estimation of Reinforced Steel: Step2: Labor Requirement for 1m3 of RCC Step 3: Equipments and sundries Step 4: Contractor’s Profit Step 5: Rate Analysis for Floors Sub Base

More

Rate Analysis: What Is It, How Does It Work ProEst

2021-6-15  For concrete rate analysis, we need first to organize the data we need for calculations. This includes materials, steel, craft, shuttering charge, and water charge. We will calculate the rate for 10m3 of concrete. The Cement: Sand and Aggregate ratio is 1:2:4, whereas the density of cement is 1440kg/m3.

More

Rate Analysis for Cement Mortar -Calculate

To calculate the quantity of cement in number of bags, we have to divide it by volume of cement of one bags. The volume of one bag of cement is 0.0347 m 3 . Therefore, number of bags of cement = Quantity of sand = For example, for a

More

What will be the cost of M25 grade concrete ?/How to

2021-9-24  The cost of M25 grade concrete per cu ft. = [INR 8371.69/- ÷ 35.314] ( 1CUM = 35.314 cu ft.) = INR 237.06/ - per cu ft. For contractor: If the concrete work is handed over to any contractor, then you have to add 10% extra as profit. The cost of M25 grade concrete done by a contractor = [INR 8371.69/- + 10% of INR 8371.69/-]

More

CENTRAL PUBLIC WORKS DEPARTMENT ANALYSIS OF

2014-9-4  This Analysis of Rates 2014 for Delhi is prepared for the use of CPWD. However, this may be used ... All leading Govt. Book Dealers in India Price : Rs. 3000/-Per Set of 2 Volumes Excluding, Postage, Packing and Delivery Charges etc. ... (1 cement: 6 fine sand) 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.172 2805.75 482.59 LABOUR: 0155 ...

More

Rate Analysis Of Brickwork Rate Analysis Of

2021-6-26  Step 1 – Calculation for cost Add 1.5% for water charges = 1.5/100 x 44785.5 = 671.8 Add 1.5% for tools plants = 1.5/100 x 44785.5 = 671.8 Add 3% for lump sum = 3/100 x 44785.5 = 1343.6 Add 10% for contractor profit =

More

Stamp Concrete Latest Price, Manufacturers Suppliers

Stamped Concrete, And 10-15 Mm ₹ 55/ Square Feet Get Quote More Than 40 Colors Society Stamp Concrete, For Flooring,... ₹ 50/ Square Feet Get Quote Stamped Concrete, >25 Mm ₹ 70/ Square Feet Get Latest Price Coverage area (application): Bathroom, Bedroom, Kitchen, Laundry, Outdoor Unit Size (mm X mm): Customized Surface Finish: Polished

More

Micro Cement Latest Price, Manufacturers

Chryso Excem Mc 40 Pre-mixed Flowable Micro Concrete ₹ 13/ Kilogram Get Quote Bronco Cemrepair Mc ₹ 16/ Kg Get Quote Sikarep Microcrete-4 Cementitious Micro Concrete, For Structure... ₹ 13/ Kg Get Quote Watch

More

How to Perform Rate Analysis for Earth Excavation?

Rate Analysis of Manual Earthwork Excavation The concept can be explained with a simple example. Consider a work where it is required to excavate a pit of following dimensions: Breadth (b) = 2000; Length (l) = 4000mm and Depth (d) = 1000mm; Steps involved in rate analysis are: Step 1: Investigate Site and Determine the tasks

More

Building Construction Rate Analysis Excel Building Cost

2021-10-18  Labours’ and materials’ rates: First class bricks = INR 4500 for each 1000 numbers. Second class bricks = INR 4000 for each 1000 numbers. Brick Ballast is equal to INR 800 for each m 3 Coarse sand is equal to INR 800 for each m 3 50 kg cement bag is equal to INR 270 for each bag Twisted bars equal to INR 5000 for each quintal

More